IURC Decision Limits Cost Recovery on Duke Energy Edwardsport IGCC Plant on Indiana

Posted by Laura Arnold  /   December 27, 2012  /   Posted in Edwardsport IGCC Plant, Office of Utility Consumer Counselor (OUCC), Uncategorized  /   No Comments

Dear Indiana DG Readers:

The Indiana Utility Regulatory Commission (IURC) this afternoon (12/27/12) approved a modified Settlement Agreement in the Duke Energy Indiana Edwardsport case.

Please find below the official IURC News Release. Download the IURC News Release HERE > http://www.in.gov/iurc/files/IURC_Decision_Limits_Cost_Recovery_on_Duke_Energy_Edwardsport_Plant.pdf

Download a copy of the order HERE > http://www.in.gov/iurc/files/Order_in_Cause_No_43114_IGCC_4_S1.pdf 

The order is 134 pages but most of the order summarizes the case and the procedural history.

The Commission Discussion and Findings begins at p. 109.

A copy of the Settlement Agreement starts at p. 123 of the 134 page document., however, since this was not a settlement signed by all the parties to the proceeding this is likely not over. More details will be covered as they unfold. Watch this blog for further developments.

Enjoy!

Laura Ann Arnold

-------------------------------------

IURC News Release
Indiana Utility Regulatory Commission
101 W. Washington St.
Suite 1500 E.
Indianapolis, IN 46204

For Immediate Release  
December 27, 2012
Contact Information:
Danielle McGrath
Office: (317) 232‐2297

IURC Decision Limits Cost Recovery on Duke Energy Edwardsport Plant

Commission approves modified settlement agreement and credits ratepayers an additional $28 million

INDIANAPOLIS – Today the Indiana Utility Regulatory Commission (IURC) modified and approved a settlement agreement reached in the Duke Energy Indiana case involving the revised cost estimate for the electric utility’s new integrated gasification combined cycle facility (IGCC) in Edwardsport, Ind.

The settlement agreement set a hard cost cap for the project at $2.595 billion (as of June 30, 2012), which prohibits Duke Energy from recovering project construction costs above this amount from retail electric customers, excluding costs related to force majeure situations defined in the agreement. It also requires the utility to absorb nearly $900 million in cost overruns given the plant is now projected to cost approximately $3.5 billion.

Although Duke Energy is limited in its recovery of project costs, the settlement agreement does allow the utility to recover financing charges accrued to fund the project’s construction. This arrangement is otherwise known as allowance for funds used during construction (AFUDC) and has been approved thus far in this case in accordance with state law.

Through a modification to the settlement agreement, the IURC also provided $28 million in additional value to ratepayers by directing Duke Energy to credit customers for cost control incentive payments found to be unwarranted, given the delays that arose from the project cost overruns. The IURC also modified the settlement agreement in such a way that if Duke Energy should recover through litigation claims more than the IGCC project costs absorbed by its shareholders, any surplus recovery is required to be returned to ratepayers.

The investment recovery sharing coupled with the other terms of the settlement agreement created value that was found to be in the public interest. The settlement agreement was reached by the utility, Nucor Steel Indiana, the Duke industrial group, and the Indiana Office of Utility Consumer Counselor. Packaged with the settlement agreement is also a guarantee by Duke Energy that it will not file a rate case prior to March 2013, nor implement one before April 2014.

For your reference, the IURC’s decision under Cause No. 43114 IGCC 4 S1 can be found online at www.in.gov/iurc. To read the “Commission Discussion and Findings” section, please go to page 109. If you need to access other case‐related documents, visit our Electronic Document System at https://myweb.in.gov/IURC/eds/. Instructions on how to best use this database can be found at www.in.gov/iurc/2666.htm.
###

The Commission is a fact‐finding body that hears evidence in cases filed before it and makes decisions based on the evidence presented in those cases. An advocate of neither the public nor the utilities, the IURC is required by state statute to make decisions that balance the interests of all parties to ensure the utilities provide adequate and reliable service at reasonable prices. For more information, please visit: www.in.gov/iurc.